A preview of a real Excel estimate, showing how quantities and prices are laid out.
| DETAILED BREAKDOWN OF ITEMS | |||||||||||||||||||
| Prepared for: | Industrial Estimating | #VALUE! | |||||||||||||||||
| Project ID: | 11102025 | ||||||||||||||||||
| Scope: | GC Estimating | ||||||||||||||||||
| SR # | Drawing # | Detail # | DESCRIPTION | UNIT | QUANTITY | WASTAGE | QUANTITY W/ WASTAGE | UNIT MANHOUR | HOURLY WAGE | LABOR COST | MAT. COST | UNIT COST | SUB COST | ||||||
| GENERAL REQUIREMENTS | |||||||||||||||||||
| 1 | Permits | LS | 1 | 0% | 1 | 0.000 | $- | $- | $- | $- | $- | ||||||||
| 2 | Supervision and Coordination | LS | 1 | 0% | 1 | 0.000 | $- | $- | $- | $185,000.00 | $185,000.00 | ||||||||
| 3 | Submittals and Shop drawings | LS | 1 | 0% | 1 | 0.000 | $- | $- | $- | $- | $- | ||||||||
| 4 | Final Cleaning | LS | 1 | 0% | 1 | 0.000 | $- | $- | $- | $25,000.00 | $25,000.00 | ||||||||
| 5 | Mobilization Costs | LS | 1 | 0% | 1 | 0.000 | $- | $- | $- | $156,000.00 | $156,000.00 | ||||||||
| 6 | Temporary Control & Facilities | LS | 1 | 0% | 1 | 0.000 | $- | $- | $- | $125,000.00 | $125,000.00 | ||||||||
| 7 | Scaffolding | LS | 1 | 0% | 1 | 0.000 | $- | $- | $- | $- | $- | ||||||||
| SUBTOTAL | $491,000 | ||||||||||||||||||
| EXISTING CONDITIONS | LABOR COST | MAT. COST | |||||||||||||||||
| DEMOLITION | |||||||||||||||||||
| SITE DEMOLITION: | $- | $- | |||||||||||||||||
| 8 | Sheet 2 | Notes/Sheet 2 | Remove And Salvage Existing Traffic Signal Poles | EA | 2 | 0% | 2 | 2.500 | $55.00 | $137.50 | $- | $137.50 | $275.00 | $275.00 | $- | ||||
| 9 | Remove Existing AC Curb In Its Entirety | LF | 80 | 0% | 80 | 0.150 | $55.00 | $8.25 | $- | $8.25 | $660.00 | $660.00 | $- | ||||||
| 10 | Remove Existing Concrete Ramp In Its Entirety | SF | 101 | 0% | 101 | 0.088 | $55.00 | $4.84 | $- | $4.84 | $490.44 | $490.44 | $- | ||||||
| 11 | Allowance To Haul-Off Of Demolished Material | LS | 1 | 0% | 1 | 0.000 | $- | $1,000.00 | $- | $1,000.00 | $1,000.00 | $1,000.00 | $- | ||||||
| $- | $- | ||||||||||||||||||
| SUBTOTAL | $2,425 | $- | $- | ||||||||||||||||
| $- | $- | ||||||||||||||||||
| CONCRETE | $- | $- | |||||||||||||||||
| CAST IN PLACE CONCRETE | $- | $- | |||||||||||||||||
| S-2 | CONTINUOUS FOOTING: | $- | $- | ||||||||||||||||
| 4/S8 | 1'-0"W x 1'-6"D Continuous Footing | LF | 304 | $- | $- | ||||||||||||||
| 12 | Concrete | CY | 17 | 10% | 19 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $10,171.33 | $4,226.44 | $5,944.89 | ||||||
| 13 | Reinforcement: (2) #4 Continuous Bar @ Top And Bottom | LBS | 508 | 10% | 558 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $1,116.90 | $502.60 | $614.29 | ||||||
| 14 | Reinforcement: #4 Bent Dowel Bars @ 32" O.C | LBS | 380 | 10% | 418 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $836.63 | $376.48 | $460.14 | ||||||
| 15 | Reinforcement: #3 Vertical Bar @ 16" O.C | LBS | 185 | 10% | 204 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $407.31 | $183.29 | $224.02 | ||||||
| 16 | Formwork | SF | 912 | 10% | 1003 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $2,257.20 | $2,257.20 | $- | ||||||
| 17 | Excavation | CY | 34 | 10% | 37 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $1,393.33 | $1,393.33 | $- | ||||||
| 18 | Backfill | CY | 20 | 10% | 22 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $1,226.13 | $1,226.13 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 13/S8 | 1'-0"W x 1'-6"D Continuous Footing | LF | 38 | $- | $- | ||||||||||||||
| 19 | Concrete | CY | 2 | 10% | 2 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $1,303.43 | $541.61 | $761.82 | ||||||
| 20 | Reinforcement: (2) #4 Continuous Bar @ Top And Bottom | LBS | 63 | 10% | 69 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $138.51 | $62.33 | $76.18 | ||||||
| 21 | Formwork | SF | 113 | 10% | 124 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $279.92 | $279.92 | $- | ||||||
| 22 | Excavation | CY | 4 | 10% | 5 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $172.79 | $172.79 | $- | ||||||
| 23 | Backfill | CY | 2 | 10% | 3 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $146.99 | $146.99 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 13/S8 | 1'-0"W x 1'-6"D Continuous Footing | LF | 38 | $- | $- | ||||||||||||||
| 24 | Concrete | CY | 2 | 10% | 2 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $1,303.43 | $541.61 | $761.82 | ||||||
| 25 | Reinforcement: (2) #4 Continuous Bar @ Top And Bottom | LBS | 63 | 10% | 69 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $138.51 | $62.33 | $76.18 | ||||||
| 26 | Formwork | SF | 113 | 10% | 124 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $279.92 | $279.92 | $- | ||||||
| 27 | Excavation | CY | 4 | 10% | 5 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $172.79 | $172.79 | $- | ||||||
| 28 | Backfill | CY | 2 | 10% | 3 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $146.99 | $146.99 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 6/S8 | 1'-6"W x 1'-9"D Widened Footing | LF | 66 | $- | $- | ||||||||||||||
| 29 | Concrete | CY | 6 | 10% | 7 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $3,846.87 | $1,598.47 | $2,248.40 | ||||||
| 30 | Reinforcement: (3) #4 Continuous Bar @ Bottom | LBS | 110 | 10% | 121 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $241.38 | $108.62 | $132.76 | ||||||
| 31 | Reinforcement: #4 Bottom Bars @ 18" O.C | LBS | 117 | 10% | 129 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $257.47 | $115.86 | $141.61 | ||||||
| 32 | Reinforcement: #3 Continuous Bars @ Top | LBS | 62 | 10% | 68 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $135.87 | $61.14 | $74.73 | ||||||
| 33 | Reinforcement: #3 Dowel Bars @ @ 32" O.C | LBS | 39 | 10% | 43 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $86.51 | $38.93 | $47.58 | ||||||
| 34 | Formwork | SF | 230 | 10% | 253 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $569.13 | $569.13 | $- | ||||||
| 35 | Excavation | CY | 9 | 10% | 9 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $351.31 | $351.31 | $- | ||||||
| 36 | Backfill | CY | 3 | 10% | 3 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $154.58 | $154.58 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 12/S8 | PAD FOOTING: | $- | $- | ||||||||||||||||
| 2'-0" x 2'-0" x 1'-6"D Pad Footing | EA | 2 | $- | $- | |||||||||||||||
| 37 | Concrete | CY | 0 | 10% | 0 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $267.67 | $111.22 | $156.44 | ||||||
| 38 | Reinforcement: (3) #4 Bars @ Bottom Each Way | LBS | 16 | 10% | 18 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $35.27 | $15.87 | $19.40 | ||||||
| 39 | Formwork | SF | 24 | 10% | 26 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $59.40 | $59.40 | $- | ||||||
| 40 | Excavation | CY | 1 | 10% | 1 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $41.25 | $41.25 | $- | ||||||
| 41 | Backfill | CY | 1 | 10% | 1 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $40.33 | $40.33 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 5/S8 | 2'-0" x 2'-0" x 2'-6"D Pad Footing | EA | 8 | $- | $- | ||||||||||||||
| 42 | Concrete | CY | 3 | 10% | 3 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $1,784.44 | $741.48 | $1,042.96 | ||||||
| 43 | Reinforcement: (3) #4 Bars Each Way At Top And Bottom | LBS | 128 | 10% | 141 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $282.16 | $126.97 | $155.19 | ||||||
| 44 | Formwork | SF | 160 | 10% | 176 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $396.00 | $396.00 | $- | ||||||
| 45 | Excavation | CY | 7 | 10% | 7 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $275.00 | $275.00 | $- | ||||||
| 46 | Backfill | CY | 4 | 10% | 5 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $268.89 | $268.89 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 12/S8 | 2'-3" x 2'-3" x 1'-6"D Pad Footing | EA | 4 | $- | $- | ||||||||||||||
| 47 | Concrete | CY | 1 | 10% | 1 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $677.53 | $281.53 | $396.00 | ||||||
| 48 | Reinforcement: (3) #4 Bars Each Way At Top And Bottom | LBS | 64 | 10% | 71 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $141.08 | $63.49 | $77.59 | ||||||
| 49 | Formwork | SF | 80 | 10% | 88 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $198.00 | $198.00 | $- | ||||||
| 50 | Excavation | CY | 3 | 10% | 4 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $137.50 | $137.50 | $- | ||||||
| 51 | Backfill | CY | 3 | 10% | 3 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $160.33 | $160.33 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 11/S8 | 2'-9" x 2'-9" x 1'-6" Pad Footing | EA | 5 | $- | $- | ||||||||||||||
| 52 | Concrete | CY | 2 | 10% | 2 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $1,265.14 | $525.70 | $739.44 | ||||||
| 53 | Reinforcement: (3) #4 Bars Each Way At Bottom | LBS | 40 | 10% | 44 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $88.18 | $39.68 | $48.50 | ||||||
| 54 | Formwork | SF | 165 | 10% | 182 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $408.38 | $408.38 | $- | ||||||
| 55 | Excavation | CY | 3 | 10% | 4 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $140.36 | $140.36 | $- | ||||||
| 56 | Backfill | CY | 2 | 10% | 2 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $94.53 | $94.53 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 10/S8 | 3'-6" x 3'-6" x 2'-6"D Pad Footing | EA | 2 | $- | $- | ||||||||||||||
| 57 | Concrete | CY | 2 | 10% | 2 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $1,366.22 | $567.70 | $798.52 | ||||||
| 58 | Reinforcement: (4) #4 Bars Each Way At Bottom | LBS | 37 | 10% | 41 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $82.30 | $37.03 | $45.26 | ||||||
| 59 | Formwork | SF | 70 | 10% | 77 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $173.25 | $173.25 | $- | ||||||
| 60 | Excavation | CY | 3 | 10% | 3 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $122.22 | $122.22 | $- | ||||||
| 61 | Backfill | CY | 1 | 10% | 1 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $50.42 | $50.42 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 8/S8 | 5'-6" x 5'-6" x 2'-0"D Pad Footing | EA | 3 | $- | $- | ||||||||||||||
| 62 | Concrete | CY | 7 | 10% | 7 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $4,048.46 | $1,682.24 | $2,366.22 | ||||||
| 63 | Reinforcement: (5) #6 Bars Each Way At Bottom | LBS | 248 | 10% | 273 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $545.23 | $245.35 | $299.87 | ||||||
| 64 | Formwork | SF | 132 | 10% | 145 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $326.70 | $326.70 | $- | ||||||
| 65 | Excavation | CY | 8 | 10% | 9 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $330.00 | $330.00 | $- | ||||||
| 66 | Backfill | CY | 2 | 10% | 2 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $92.77 | $92.77 | $- | ||||||
| $- | $- | ||||||||||||||||||
| MAT FOOTING: | $- | $- | |||||||||||||||||
| 7/S8 | 1'-6"D Mat Footing | SF | 27 | $- | $- | ||||||||||||||
| 67 | Concrete | CY | 2 | 10% | 2 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $916.76 | $380.94 | $535.82 | ||||||
| 68 | Reinforcement: #4 Bars @ 12" O.C Each Way At Top And Bottom | LBS | 73 | 10% | 81 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $161.07 | $72.48 | $88.59 | ||||||
| 69 | Formwork | SF | 45 | 10% | 50 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $111.38 | $111.38 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 9/S8 | GRADE BEAM: | $- | $- | ||||||||||||||||
| 1'-0" x 1'-4"D Grade Beam | LF | 12 | $- | $- | |||||||||||||||
| 70 | Concrete | CY | 1 | 10% | 1 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $367.42 | $152.67 | $214.75 | ||||||
| 71 | Reinforcement: (2) #4 Continuous Bars At Top And Bottom | LBS | 39 | 10% | 43 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $85.24 | $38.36 | $46.88 | ||||||
| 72 | Formwork | SF | 31 | 10% | 34 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $76.37 | $76.37 | $- | ||||||
| 73 | Excavation | CY | 1 | 10% | 1 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $35.36 | $35.36 | $- | ||||||
| 74 | Backfill | CY | 0 | 10% | 0 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $17.93 | $17.93 | $- | ||||||
| $- | $- | ||||||||||||||||||
| 9/S8 | CONCRETE CURB: | $- | $- | ||||||||||||||||
| 4"W x 9"D Concrete Curb | LF | 379 | $- | $- | |||||||||||||||
| 75 | Concrete | CY | 8 | 10% | 9 | 3.500 | $65.00 | $227.50 | $320.00 | $547.50 | $4,734.13 | $1,967.15 | $2,766.98 | ||||||
| 76 | Reinforcement: #3 Continuous Bar | LBS | 178 | 10% | 196 | 0.015 | $60.00 | $0.90 | $1.10 | $2.00 | $391.89 | $176.35 | $215.54 | ||||||
| 77 | Formwork | SF | 569 | 10% | 625 | 0.050 | $45.00 | $2.25 | $- | $2.25 | $1,407.04 | $1,407.04 | $- | ||||||
| 78 | Excavation | CY | 11 | 10% | 12 | 0.750 | $50.00 | $37.50 | $- | $37.50 | $434.27 | $434.27 | $- | ||||||
| 79 | Backfill | CY | 3 | 10% | 4 | 1.100 | $50.00 | $55.00 | $- | $55.00 | $193.63 | $193.63 | $- | ||||||
| $- | $- | ||||||||||||||||||
| CONCRETE SLAB: | $- | $- | |||||||||||||||||
| Plan Notes @ S2 | 4" Thk. Slab On Grade As: | SF | 8182 | $- | $- | ||||||||||||||
| 80 | Concrete | CY | 100 | 10% | 110 | 3.150 | $65.00 | $204.75 | $320.00 | $524.75 | $57,724 | $22,523.00 | $35,200.78 | ||||||
| 81 | 6x6 W1.4xW1.4 W.W.R OR
#3 Bars @ 18" O.C OR Tuf-Strand SF Dosed @ 3#/YD3 | SF | 8182 | 10% | 9000 | 0.012 | $60.00 | $0.72 | $0.86 | $1.58 | $14,220 | $6,480.14 | $7,740.17 | ||||||
| 82 | 10 MIL. Vapor Barrier | SF | 8182 | 10% | 9000 | 0.010 | $50.00 | $0.50 | $0.48 | $0.98 | $8,820 | $4,500.10 | $4,320.10 | ||||||
| 83 | Prepared Well Compacted Sub Base | SF | 8182 | 10% | 9000 | 0.005 | $50.00 | $0.25 | $0.45 | $0.70 | $6,300 | $2,250.05 | $4,050.09 | ||||||
| 84 | Prepared Well Compacted Subgrade | SF | 8182 | 10% | 9000 | 0.004 | $50.00 | $0.20 | $- | $0.20 | $1,800 | $1,800.04 | $- | ||||||
| 85 | Control Joints @ 15'-0" O.C | LF | 545 | 10% | 600 | 0.020 | $65.00 | $1.30 | $0.17 | $1.47 | $882 | $780.02 | $102.00 | ||||||
| 86 | Expansion Joints @ 25'-0" O.C | LF | 327 | 10% | 360 | 0.020 | $65.00 | $1.30 | $3.25 | $4.55 | $1,638 | $468.01 | $1,170.03 | ||||||
| $- | $- | ||||||||||||||||||
| Slab Thicken Edge | LF | 379 | $- | $- | |||||||||||||||
| 87 | Concrete | CY | 3 | 10% | 3 | 3.150 | $65.00 | $204.75 | $320.00 | $524.75 | $1,621 | $632.30 | $988.21 | ||||||
| $- | $- | ||||||||||||||||||
| SUBTOTAL | $142,972 | $- | $- | ||||||||||||||||
| $- | $- | ||||||||||||||||||
| MASONRY | $- | $- | |||||||||||||||||
| UNIT MASONRY | $- | $- | |||||||||||||||||
| STONE MASONRY | $- | $- | |||||||||||||||||
| 88 | A-5.0 | A-5.0 | "C" Stone Veneer TBD | SF | 3725 | 10% | 4098 | 0.150 | $62.00 | $9.30 | $18.98 | $28.28 | $115,884.43 | $38,109.09 | $77,775.33 | ||||
| 89 | Brick Veneer Ties Vertical Spacing 8" O.C Horizontal Spacing 16" O.C Assumed | EA | 4199 | 10% | 4619 | 0.005 | $62.00 | $0.31 | $0.35 | $0.66 | $3,048.49 | $1,431.87 | $1,616.63 | ||||||
| $- | $- | ||||||||||||||||||
Showing the first 150 rows of the sheet.
Warehouses, Plants & Heavy Facilities
Industrial projects involve heavy loads, specialised systems, and tight schedules. Our estimators price warehouses, manufacturing plants, cold storage, and distribution centres with careful attention to structure, slabs, and process utilities.
Thick slabs, pits, equipment pads, and reinforced foundations quantified precisely.
Structural frames, cladding, insulation, and roofing priced accurately.
Power distribution, compressed air, process piping, and ventilation scopes.
Dock levellers, doors, bollards, and canopies included in the estimate.
Heavy-duty paving, drainage, and yard improvements for truck traffic.
Estimates for operating facilities with working-around-production allowances.

Why Choose Estimating Canada
Industrial buildings look simple from the outside, but the cost is in the floor, the structure and the services: slab loads, dock doors, clear heights, heavy electrical and sprinkler systems designed for stored goods.
We prepare industrial takeoffs and estimates for warehouses, manufacturing buildings and distribution centres, from pre-engineered metal buildings to concrete tilt-up.
Snow loads shape the roof structure, and frost protection shapes footings and slab edges. Heating and make-up air for large open buildings carry their own cost. Estimates are normally shown before tax.
Small industrial takeoffs are normally ready in about 4 to 6 hours and larger projects in 6 to 48 hours, depending on size and urgency.
Yes. The supplier package is entered as a line, with foundations, slab and finishes priced around it.
Yes, as separate sections.
We price what is shown on the drawings and list what is excluded.
Yes, including panels, bracing and erection allowances.