Industrial Estimate — Takeoff Breakdown
DETAILED BREAKDOWN OF ITEMS
Prepared for:Industrial Estimating#VALUE!
Project ID:11102025
Scope:GC Estimating
SR #Drawing #Detail #DESCRIPTIONUNITQUANTITYWASTAGEQUANTITY W/ WASTAGEUNIT MANHOURHOURLY WAGELABOR COSTMAT. COSTUNIT COSTSUB COST
GENERAL REQUIREMENTS
1PermitsLS10%10.000 $- $- $- $- $-
2Supervision and CoordinationLS10%10.000 $- $- $- $185,000.00 $185,000.00
3Submittals and Shop drawingsLS10%10.000 $- $- $- $- $-
4Final CleaningLS10%10.000 $- $- $- $25,000.00 $25,000.00
5Mobilization CostsLS10%10.000 $- $- $- $156,000.00 $156,000.00
6Temporary Control & FacilitiesLS10%10.000 $- $- $- $125,000.00 $125,000.00
7ScaffoldingLS10%10.000 $- $- $- $- $-
SUBTOTAL $491,000
EXISTING CONDITIONSLABOR COSTMAT. COST
DEMOLITION
SITE DEMOLITION: $- $-
8Sheet 2Notes/Sheet 2Remove And Salvage Existing Traffic Signal PolesEA20%22.500 $55.00 $137.50 $- $137.50 $275.00 $275.00 $-
9Remove Existing AC Curb In Its EntiretyLF800%800.150 $55.00 $8.25 $- $8.25 $660.00 $660.00 $-
10Remove Existing Concrete Ramp In Its EntiretySF1010%1010.088 $55.00 $4.84 $- $4.84 $490.44 $490.44 $-
11Allowance To Haul-Off Of Demolished MaterialLS10%10.000 $- $1,000.00 $- $1,000.00 $1,000.00 $1,000.00 $-
$- $-
SUBTOTAL $2,425 $- $-
$- $-
CONCRETE $- $-
CAST IN PLACE CONCRETE $- $-
S-2CONTINUOUS FOOTING: $- $-
4/S81'-0"W x 1'-6"D Continuous Footing LF304 $- $-
12ConcreteCY1710%193.500 $65.00 $227.50 $320.00 $547.50 $10,171.33 $4,226.44 $5,944.89
13Reinforcement: (2) #4 Continuous Bar @ Top And BottomLBS50810%5580.015 $60.00 $0.90 $1.10 $2.00 $1,116.90 $502.60 $614.29
14Reinforcement: #4 Bent Dowel Bars @ 32" O.C LBS38010%4180.015 $60.00 $0.90 $1.10 $2.00 $836.63 $376.48 $460.14
15Reinforcement: #3 Vertical Bar @ 16" O.CLBS18510%2040.015 $60.00 $0.90 $1.10 $2.00 $407.31 $183.29 $224.02
16FormworkSF91210%10030.050 $45.00 $2.25 $- $2.25 $2,257.20 $2,257.20 $-
17ExcavationCY3410%370.750 $50.00 $37.50 $- $37.50 $1,393.33 $1,393.33 $-
18BackfillCY2010%221.100 $50.00 $55.00 $- $55.00 $1,226.13 $1,226.13 $-
$- $-
13/S81'-0"W x 1'-6"D Continuous Footing LF38 $- $-
19ConcreteCY210%23.500 $65.00 $227.50 $320.00 $547.50 $1,303.43 $541.61 $761.82
20Reinforcement: (2) #4 Continuous Bar @ Top And BottomLBS6310%690.015 $60.00 $0.90 $1.10 $2.00 $138.51 $62.33 $76.18
21FormworkSF11310%1240.050 $45.00 $2.25 $- $2.25 $279.92 $279.92 $-
22ExcavationCY410%50.750 $50.00 $37.50 $- $37.50 $172.79 $172.79 $-
23BackfillCY210%31.100 $50.00 $55.00 $- $55.00 $146.99 $146.99 $-
$- $-
13/S81'-0"W x 1'-6"D Continuous Footing LF38 $- $-
24ConcreteCY210%23.500 $65.00 $227.50 $320.00 $547.50 $1,303.43 $541.61 $761.82
25Reinforcement: (2) #4 Continuous Bar @ Top And BottomLBS6310%690.015 $60.00 $0.90 $1.10 $2.00 $138.51 $62.33 $76.18
26FormworkSF11310%1240.050 $45.00 $2.25 $- $2.25 $279.92 $279.92 $-
27ExcavationCY410%50.750 $50.00 $37.50 $- $37.50 $172.79 $172.79 $-
28BackfillCY210%31.100 $50.00 $55.00 $- $55.00 $146.99 $146.99 $-
$- $-
6/S81'-6"W x 1'-9"D Widened Footing LF66 $- $-
29ConcreteCY610%73.500 $65.00 $227.50 $320.00 $547.50 $3,846.87 $1,598.47 $2,248.40
30Reinforcement: (3) #4 Continuous Bar @ BottomLBS11010%1210.015 $60.00 $0.90 $1.10 $2.00 $241.38 $108.62 $132.76
31Reinforcement: #4 Bottom Bars @ 18" O.C LBS11710%1290.015 $60.00 $0.90 $1.10 $2.00 $257.47 $115.86 $141.61
32Reinforcement: #3 Continuous Bars @ TopLBS6210%680.015 $60.00 $0.90 $1.10 $2.00 $135.87 $61.14 $74.73
33Reinforcement: #3 Dowel Bars @ @ 32" O.CLBS3910%430.015 $60.00 $0.90 $1.10 $2.00 $86.51 $38.93 $47.58
34FormworkSF23010%2530.050 $45.00 $2.25 $- $2.25 $569.13 $569.13 $-
35ExcavationCY910%90.750 $50.00 $37.50 $- $37.50 $351.31 $351.31 $-
36BackfillCY310%31.100 $50.00 $55.00 $- $55.00 $154.58 $154.58 $-
$- $-
12/S8PAD FOOTING: $- $-
2'-0" x 2'-0" x 1'-6"D Pad Footing EA2 $- $-
37ConcreteCY010%03.500 $65.00 $227.50 $320.00 $547.50 $267.67 $111.22 $156.44
38Reinforcement: (3) #4 Bars @ Bottom Each WayLBS1610%180.015 $60.00 $0.90 $1.10 $2.00 $35.27 $15.87 $19.40
39FormworkSF2410%260.050 $45.00 $2.25 $- $2.25 $59.40 $59.40 $-
40ExcavationCY110%10.750 $50.00 $37.50 $- $37.50 $41.25 $41.25 $-
41BackfillCY110%11.100 $50.00 $55.00 $- $55.00 $40.33 $40.33 $-
$- $-
5/S82'-0" x 2'-0" x 2'-6"D Pad Footing EA8 $- $-
42ConcreteCY310%33.500 $65.00 $227.50 $320.00 $547.50 $1,784.44 $741.48 $1,042.96
43Reinforcement: (3) #4 Bars Each Way At Top And BottomLBS12810%1410.015 $60.00 $0.90 $1.10 $2.00 $282.16 $126.97 $155.19
44FormworkSF16010%1760.050 $45.00 $2.25 $- $2.25 $396.00 $396.00 $-
45ExcavationCY710%70.750 $50.00 $37.50 $- $37.50 $275.00 $275.00 $-
46BackfillCY410%51.100 $50.00 $55.00 $- $55.00 $268.89 $268.89 $-
$- $-
12/S82'-3" x 2'-3" x 1'-6"D Pad Footing EA4 $- $-
47ConcreteCY110%13.500 $65.00 $227.50 $320.00 $547.50 $677.53 $281.53 $396.00
48Reinforcement: (3) #4 Bars Each Way At Top And BottomLBS6410%710.015 $60.00 $0.90 $1.10 $2.00 $141.08 $63.49 $77.59
49FormworkSF8010%880.050 $45.00 $2.25 $- $2.25 $198.00 $198.00 $-
50ExcavationCY310%40.750 $50.00 $37.50 $- $37.50 $137.50 $137.50 $-
51BackfillCY310%31.100 $50.00 $55.00 $- $55.00 $160.33 $160.33 $-
$- $-
11/S82'-9" x 2'-9" x 1'-6" Pad Footing EA5 $- $-
52ConcreteCY210%23.500 $65.00 $227.50 $320.00 $547.50 $1,265.14 $525.70 $739.44
53Reinforcement: (3) #4 Bars Each Way At BottomLBS4010%440.015 $60.00 $0.90 $1.10 $2.00 $88.18 $39.68 $48.50
54FormworkSF16510%1820.050 $45.00 $2.25 $- $2.25 $408.38 $408.38 $-
55ExcavationCY310%40.750 $50.00 $37.50 $- $37.50 $140.36 $140.36 $-
56BackfillCY210%21.100 $50.00 $55.00 $- $55.00 $94.53 $94.53 $-
$- $-
10/S83'-6" x 3'-6" x 2'-6"D Pad Footing EA2 $- $-
57ConcreteCY210%23.500 $65.00 $227.50 $320.00 $547.50 $1,366.22 $567.70 $798.52
58Reinforcement: (4) #4 Bars Each Way At BottomLBS3710%410.015 $60.00 $0.90 $1.10 $2.00 $82.30 $37.03 $45.26
59FormworkSF7010%770.050 $45.00 $2.25 $- $2.25 $173.25 $173.25 $-
60ExcavationCY310%30.750 $50.00 $37.50 $- $37.50 $122.22 $122.22 $-
61BackfillCY110%11.100 $50.00 $55.00 $- $55.00 $50.42 $50.42 $-
$- $-
8/S85'-6" x 5'-6" x 2'-0"D Pad FootingEA3 $- $-
62ConcreteCY710%73.500 $65.00 $227.50 $320.00 $547.50 $4,048.46 $1,682.24 $2,366.22
63Reinforcement: (5) #6 Bars Each Way At BottomLBS24810%2730.015 $60.00 $0.90 $1.10 $2.00 $545.23 $245.35 $299.87
64FormworkSF13210%1450.050 $45.00 $2.25 $- $2.25 $326.70 $326.70 $-
65ExcavationCY810%90.750 $50.00 $37.50 $- $37.50 $330.00 $330.00 $-
66BackfillCY210%21.100 $50.00 $55.00 $- $55.00 $92.77 $92.77 $-
$- $-
MAT FOOTING: $- $-
7/S81'-6"D Mat Footing SF27 $- $-
67ConcreteCY210%23.500 $65.00 $227.50 $320.00 $547.50 $916.76 $380.94 $535.82
68Reinforcement: #4 Bars @ 12" O.C Each Way At Top And BottomLBS7310%810.015 $60.00 $0.90 $1.10 $2.00 $161.07 $72.48 $88.59
69FormworkSF4510%500.050 $45.00 $2.25 $- $2.25 $111.38 $111.38 $-
$- $-
9/S8GRADE BEAM: $- $-
1'-0" x 1'-4"D Grade BeamLF12 $- $-
70ConcreteCY110%13.500 $65.00 $227.50 $320.00 $547.50 $367.42 $152.67 $214.75
71Reinforcement: (2) #4 Continuous Bars At Top And BottomLBS3910%430.015 $60.00 $0.90 $1.10 $2.00 $85.24 $38.36 $46.88
72FormworkSF3110%340.050 $45.00 $2.25 $- $2.25 $76.37 $76.37 $-
73ExcavationCY110%10.750 $50.00 $37.50 $- $37.50 $35.36 $35.36 $-
74BackfillCY010%01.100 $50.00 $55.00 $- $55.00 $17.93 $17.93 $-
$- $-
9/S8CONCRETE CURB: $- $-
4"W x 9"D Concrete CurbLF379 $- $-
75ConcreteCY810%93.500 $65.00 $227.50 $320.00 $547.50 $4,734.13 $1,967.15 $2,766.98
76Reinforcement: #3 Continuous BarLBS17810%1960.015 $60.00 $0.90 $1.10 $2.00 $391.89 $176.35 $215.54
77FormworkSF56910%6250.050 $45.00 $2.25 $- $2.25 $1,407.04 $1,407.04 $-
78ExcavationCY1110%120.750 $50.00 $37.50 $- $37.50 $434.27 $434.27 $-
79BackfillCY310%41.100 $50.00 $55.00 $- $55.00 $193.63 $193.63 $-
$- $-
CONCRETE SLAB: $- $-
Plan Notes @ S24" Thk. Slab On Grade As:SF8182 $- $-
80ConcreteCY10010%1103.150 $65.00 $204.75 $320.00 $524.75 $57,724 $22,523.00 $35,200.78
816x6 W1.4xW1.4 W.W.R OR
#3 Bars @ 18" O.C OR
Tuf-Strand SF Dosed @ 3#/YD3
SF818210%90000.012 $60.00 $0.72 $0.86 $1.58 $14,220 $6,480.14 $7,740.17
8210 MIL. Vapor BarrierSF818210%90000.010 $50.00 $0.50 $0.48 $0.98 $8,820 $4,500.10 $4,320.10
83Prepared Well Compacted Sub BaseSF818210%90000.005 $50.00 $0.25 $0.45 $0.70 $6,300 $2,250.05 $4,050.09
84Prepared Well Compacted SubgradeSF818210%90000.004 $50.00 $0.20 $- $0.20 $1,800 $1,800.04 $-
85Control Joints @ 15'-0" O.CLF54510%6000.020 $65.00 $1.30 $0.17 $1.47 $882 $780.02 $102.00
86Expansion Joints @ 25'-0" O.CLF32710%3600.020 $65.00 $1.30 $3.25 $4.55 $1,638 $468.01 $1,170.03
$- $-
Slab Thicken EdgeLF379 $- $-
87ConcreteCY310%33.150 $65.00 $204.75 $320.00 $524.75 $1,621 $632.30 $988.21
$- $-
SUBTOTAL $142,972 $- $-
$- $-
MASONRY $- $-
UNIT MASONRY $- $-
STONE MASONRY $- $-
88A-5.0A-5.0"C" Stone Veneer TBDSF372510%40980.150 $62.00 $9.30 $18.98 $28.28 $115,884.43 $38,109.09 $77,775.33
89Brick Veneer Ties
Vertical Spacing 8" O.C
Horizontal Spacing 16" O.C
Assumed
EA419910%46190.005 $62.00 $0.31 $0.35 $0.66 $3,048.49 $1,431.87 $1,616.63
$- $-

Showing the first 150 rows of the sheet.

Warehouses, Plants & Heavy Facilities

Industrial Estimating

Industrial projects involve heavy loads, specialised systems, and tight schedules. Our estimators price warehouses, manufacturing plants, cold storage, and distribution centres with careful attention to structure, slabs, and process utilities.

What's Included

Heavy Slab & Foundation Takeoffs

Thick slabs, pits, equipment pads, and reinforced foundations quantified precisely.

Pre-Engineered Steel Buildings

Structural frames, cladding, insulation, and roofing priced accurately.

Process Utilities & Services

Power distribution, compressed air, process piping, and ventilation scopes.

Dock & Loading Equipment

Dock levellers, doors, bollards, and canopies included in the estimate.

Sitework & Paving

Heavy-duty paving, drainage, and yard improvements for truck traffic.

Expansion & Retrofit Pricing

Estimates for operating facilities with working-around-production allowances.

Industrial Estimating

Why Choose Estimating Canada

Built For Contractors Who Need It Right

Experience with warehouse, manufacturing, and cold-storage builds
Heavy-duty structural and civil scopes covered
Delivered as an itemized Excel and PDF report ready for your bid
Small jobs in about 4–6 hours, large projects in 6–48 hours, with free revisions on addenda
Confidential handling of your plans and bid documents
Get a Free Quote

Industrial estimating services for Canadian contractors

Industrial buildings look simple from the outside, but the cost is in the floor, the structure and the services: slab loads, dock doors, clear heights, heavy electrical and sprinkler systems designed for stored goods.

We prepare industrial takeoffs and estimates for warehouses, manufacturing buildings and distribution centres, from pre-engineered metal buildings to concrete tilt-up.

| What we price

Warehouses and distribution centres
Pre-engineered metal buildings and tilt-up concrete
Manufacturing and light industrial plants
Dock doors, levellers and loading areas
Mezzanines, offices and mechanical rooms inside the building

| What drives industrial cost

Heavy slab on grade with joints, reinforcing and flatness requirements
Structure: steel frames, joists, deck and roof systems
Large electrical services, high-bay lighting and power for equipment
Sprinkler systems designed for the stored commodity
Site work, paving and truck courts

| Canadian industrial detail

Snow loads shape the roof structure, and frost protection shapes footings and slab edges. Heating and make-up air for large open buildings carry their own cost. Estimates are normally shown before tax.

| Timing

Small industrial takeoffs are normally ready in about 4 to 6 hours and larger projects in 6 to 48 hours, depending on size and urgency.

Frequently asked questions

Do you price pre-engineered metal buildings?

Yes. The supplier package is entered as a line, with foundations, slab and finishes priced around it.

Do you price site work and paving?

Yes, as separate sections.

Can you price process piping and equipment connections?

We price what is shown on the drawings and list what is excluded.

Do you price tilt-up concrete?

Yes, including panels, bracing and erection allowances.

Get a Quote

Get a Quote for Industrial Estimating

We’re online now — replies in minutes

Tell us what you need and we’ll get back to you within minutes.

No file chosen

PDF, images, Word, Excel, DWG/DXF or ZIP — max 100 MB